Cornwall Perimeter Highway project update – October 3 to 8

October 3, 2016
Share this page

Work continues on Phase 1 of the Cornwall Perimeter Highway with activity planned throughout daylight hours from Monday, Oct. 3 to Saturday, Oct. 8.

Traffic flow on the Trans Canada Highway will remain in both directions but may be reduced from four to two lanes at times, which will result in delays. Motorists may wish to use alternative routes such as Route 2 and the Warren Grove Road when entering and leaving Charlottetown, especially during morning and evening commuting hours

Activities this week focus on installing of storm water handling systems and constructing concrete bases for highway lights. These activities will require heavy equipment in the traveled portion of the highway project.

Drivers are asked to be alert and courteous and to operate with concern for the safety of workers, pedestrians and their fellow motorists. We appreciate the patience of the traveling public during delays caused by construction.

Phase 1 of the Cornwall Perimeter Highway is proceeding on schedule, with completion expected in mid-to-late November.

Media Contact:

Ron Ryder

Department of Transportation, Infrastructure and Energy

rrryder@gov.pe.ca    

(902)368-5112

General Inquiries

Department of Transportation and Infrastructure

3rd Floor, Jones Building

11 Kent Street,

P.O. Box 2000,

Charlottetown, PE C1A 7N8

Phone: 902-368-5100

Fax: 902-368-5395

Access PEI/Highway Safety Head Office

33 Riverside Drive

Charlottetown, PE

Phone: 902-368-5200

accesspeicharlottetown@gov.pe.ca

Road-Related Inquiries: roads@gov.pe.ca

Report Transportation Problems